A Forvr concept. Stannard & Lowe is a fictional firm; names, reviews and figures are illustrative. forvr.org
Stannard & Lowe

Projects

Every finished job, with the price we quoted, the price you paid, and the weeks we planned against the weeks it took. 28 of the last 30 finished on time.

030 · finished Sep 2026

Sonning

Rear extension, 38 m²

Quoted
£142k
Final
£142k
Weeks planned
16
Weeks taken
15

Brick to match the 1930s house, steel and glazing across the full width.

029 · finished Aug 2026

Wargrave

Kitchen and vaulted roof, 31 m²

Quoted
£118k
Final
£121k
Weeks planned
14
Weeks taken
14

Client added a second roof light in week 6, priced and signed before we fitted it.

028 · finished Jul 2026

Caversham

Hip-to-gable loft, 2 bedrooms

Quoted
£74k
Final
£74k
Weeks planned
10
Weeks taken
11

One week late: steel delivery slipped. We paid the £150 under the contract.

027 · finished Jun 2026

Henley-on-Thames

Side return, 22 m²

Quoted
£88k
Final
£88k
Weeks planned
12
Weeks taken
11

Party wall agreed in four weeks, which set the start date.

026 · finished May 2026

Twyford

Wrap-around extension, 46 m²

Quoted
£176k
Final
£179k
Weeks planned
20
Weeks taken
20

Drainage diverted after survey, priced in the quote, not discovered later.

025 · finished Apr 2026

Woodley

Dormer loft, 1 bedroom and shower

Quoted
£61k
Final
£61k
Weeks planned
9
Weeks taken
9

Family stayed in the house throughout.